Organisation/company in control of the operation.
-
Named individual responsible for the activity and its safety.
-
Name of method statement originator and authorisation date.
-
Arrangements for changing/deviating from method statement.
-
General description of activity.
-
Location of activity including access and restrictions.
-
General working environment considerations, e.g. temperature and wind speed.
-
Protection of others, e.g. members of the public.
-
Emergency procedures, including location of emergency equipment.
-
Identity of operatives (and any specific training or certification required).
-
Requirements for Personal Protective Equipment.
-
Plant and equipment used, including safety precautions and restrictions.
-
Materials information e.g. hazard information and storage/transport requirements.
-
Work sequence, including associated risks and required control measures for each stage.
-
Safety checks/clearances at specific stages.
-
Work sequence, including associated risks and required control measures for each stage.
-
Final clearance that activity is completed to specification.